July 24, 2013 - Forming up the roof.
July 26, 2013 - Forming up the roof.
July 29, 2013 - Pouring the roof.
July 31, 2013 - Wow. Its come a long way ... Still a long way to go.
August 4, 2013 - Laying out driveway.
August 5, 2013
August 8, 2013 - Forms off and cleanup.
August 10 - Moving trees.
August 14, 2013
August 15, 2013 - Steve and I painted on the rubberized sealer over the sealed concrete. We use Black Jack brand "Rubr-Coat #57."
August 16, 2013
August 17, 2013 - Drain work.
August 19, 2013 - Ceiling painted.
August 21, 2013 - Backfilling.
August 22, 2013 - Backfilling and cleanup.
August 23, 2013 - Roadwork, backfilling, masonry work.
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
![]() |
![]() |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|